Laserfiche WebLink
TECHNICAL ADVISORY GROUP RECOMMENDATION <br />TAG_CONTRACTINGRECOMMENDATIONFORM_WP-43CD_MEYER_CO-06_2019-0213 7 <br />19.Time Extension: The Contractor has requested and the EOR agrees with and recommends 3.75 (round to <br />4 for the Contract Times) days be added to the following Contract Times: <br />a.Add four (4) days to Substantial Completion, changing it to November 6, 2018. <br />b.Add four (4) days to Milestone 8.b (All work, except Pump Station mechanical and electrical <br />components and finishes), changing it to September 19, 2018. <br />c.Add four (4) days to Milestone 9 (Pump Station Operation), changing it to October 19, 2018. <br />ATTACHMENT(S):  <br />1.Draft Change Order No. 6 with unit price schedule <br />2. HMG Change Order No. 6 recommendation and supporting documentation memo <br />Submitted by:  <br />John Glatzmaier  <br />Jacobs    <br />Metro Flood Diversion Project  <br />Date  <br />Nathan Boerboom, Diversion Authority Project  <br />Manager  <br />Matt Stamness, Assistant Cass County Engineer,  <br />Diversion Authority Project Manager  <br />Concur:  Non‐Concur:  Concur:  Non‐Concur <br />Robert Zimmerman, Moorhead City Engineer Jason Benson, Cass County Engineer  <br />Concur:  Non‐Concur:  Concur:Non‐Concur <br />David Overbo, Clay County Engineer  <br />Concur:Non‐Concur:   <br />February 13, 2019 <br />February 14, 2019 <br />February 21, 2019 <br />February 21, 2019 <br />February 21, 2019