Laserfiche WebLink
TECHNICAL ADVISORY GROUP RECOMMENDATION <br />TAG_CONTRACTINGRECOMMENDATIONFORM_WP-43CD_MEYER_CO-06_2019-0213 6 <br />driveway apron flare.  The Contractor incurred additional costs to complete this work.  The Engineer  <br />concurs and recommends this cost change.  <br />a. This change adds Bid Item 0201, CO‐6: Concrete Driveway 119 Oxbow Drive: lump sum quantity  <br />of 1.0 LS at the Contract Unit Price of $5,362.96 per LS for a price increase of $5,362.96.  <br />13. Upsizing Neutral Wire from #3/0 to #500 (COR 9000070): The neutral wire as designed did not meet NEC  <br />code and had to be replaced with a larger, code compliant neutral wire.  The Contractor incurred  <br />additional costs to complete this work.  The Engineer concurs and recommends this cost change.  <br />a. This change adds Bid Item 0202, CO‐6: Upsizing Neutral Wire from #3/0 to #500: lump sum  <br />quantity of 1.0 LS at the Contract Unit Price of $1,241.88 per LS for a price increase of $1,241.88.  <br />14. Electrical Material Price Increase (COR 9000071): The Contractor incurred additional electrical material  <br />costs due to a purchase delay and cost increase after the Owner issued work suspension directive.  The  <br />Engineer concurs and recommends this cost change.    <br />a. This change adds Bid Item 0203, CO‐6: Electrical Material Price Increase: lump sum quantity of  <br />1.0 LS at the Contract Unit Price of $1,935.78 per LS for a price increase of $$1,935.78.  <br />15. Zone 1 Seed Modification ‐ Include Oats Cover Crop (COR 9000072): The Owner ordered seeding  <br />changes for a portion of project area due to future project schedule changes caused by the Federal  <br />injunction against construction on a portion of the OHB Ring Levee and Contractor incurred additional  <br />turf establishment costs.  The Engineer concurs and recommends this cost change.      <br />a. This change adds Bid Item 0204, CO‐6: Zone 1 Seed Modification ‐ Include Oats Cover Crop: unit  <br />rate quantity of 15.0 AC at the Contract Unit Price of $508.20 per AC for a price increase of  <br />$7,623.00.  <br />16. Additional 20A/3 Pole Circuit Breaker (COR 9000073): During shop drawing review it was determined  <br />that an additional circuit breaker was required for the pump station overhead door.  This work is a  <br />change from the original Contract Documents. The Contractor incurred additional costs to supply and  <br />install the circuit breaker.  The Engineer concurs and recommends this cost change.    <br />a. This change adds Bid Item 0205, CO‐6: Additional 20A/3 Pole Circuit Breaker: lump sum quantity  <br />of 1.0 LS at the Contract Unit Price of $800.22 per LS for a price increase of $800.22.  <br />17. Upsizing Neutral Wire (COR 9000074): During shop drawing review it was determined that the NEC code  <br />required a larger wire size from the generator to the Automatic Transfer Switch (ATS).  This work is a  <br />change from the original Contract Documents. The Contractor incurred additional costs to supply the  <br />larger wire.  The Engineer concurs and recommends this cost change.    <br />a. This change adds Bid Item 0206, CO‐6: Upsizing Neutral Wire: lump sum quantity of 1.0 LS at the  <br />Contract Unit Price of $773.63 per LS for a price increase of $773.63.  <br />18. Additional Pump Test Equipment and Gauges (COR 9000075): The Owner requested that temporary  <br />pump testing equipment be installed permanently and made part of the project.  This work is a change  <br />from the original Contract Documents. The Contractor incurred additional costs to provide this  <br />equipment for the project.  The Engineer concurs and recommends this cost change.    <br />a. This change adds Bid Item 0207, CO‐6: Additional Pump Test Equipment and Gauges: lump sum  <br />quantity of 1.0 LS at the Contract Unit Price of $3,036.04 per LS for a price increase of $3,036.04.