Laserfiche WebLink
TECHNICAL ADVISORY GROUP RECOMMENDATION <br /> <br />TAG_CONTRACTINGRECOMMENDATIONFORM_WP-43CD_MEYER_CO-06_2019-0213 5 <br />risk of future maintenance.  This work was not included in the original Contract Documents.  The  <br />Engineer directed the Contractor to complete the work on a time and materials basis.   <br />a. This change adds Bid Item 0194, CO‐6: Remove Control Structures: lump sum quantity 1.0 LS at  <br />the Contract Unit Price of $1,581.00 per LS for a price increase of $1,581.00.  <br />6. Oxbow Drive Curb Repair (COR 9000059): The Owner and Engineer directed repairs to damaged curb  <br />and gutter that was installed under this Contract.  A portion of the damage was caused by others and  <br />the Contractor incurred additional costs to repair damage by others.  The Engineer concurs and  <br />recommends this cost change.       <br />a. This change adds Bid Item 0195, CO‐6: Oxbow Drive Curb Repair: lump sum quantity of 1.0 LS at  <br />the Contract Unit Price of $3,828.00 per LS for a price increase of $3,828.00.  <br />7. Additional Pavement Markings (COR 9000060): The Owner requested additional pavement markings at  <br />the intersection of Hwy 81 and Oxbow Drive that were not part of the original Contract Documents.  The  <br />Contractor incurred additional costs to complete this work.  The Engineer concurs and recommends this  <br />cost change.   <br />a. This change adds Bid Item 0196, CO‐6: Additional Pavement Markings: lump sum quantity of 1.0  <br />LS at the Contract Unit Price of $2,864.29 per LS for a price increase of $2,864.29.  <br />8. Additional Ditch Grading (COR 9000063): The Owner requested Hwy 81 ditch grading at the intersection  <br />of Hwy 81 and Oxbow Drive that was not part of the original Contract Documents.  The Contractor  <br />incurred additional costs to complete this work.  The Engineer concurs and recommends this cost  <br />change.  <br />a. This change adds Bid Item 0197, CO‐6: Additional Ditch Grading: lump sum quantity of 1.0 LS at  <br />the Contract Unit Price of $12,871.38 per LS for a price increase of $12,871.38.  <br />9. Metal Roofing Price Increase (COR 9000064): The Contractor incurred additional roofing material costs  <br />due to a purchase delay and cost increase after the Owner issued work suspension directive.  The  <br />Engineer concurs and recommends this cost change.  <br />a. This change adds Bid Item 0198, CO‐6: Metal Roofing Price Increase: lump sum quantity of 1.0 LS  <br />at the Contract Unit Price of $3,198.20 per LS for a price increase of $3,198.20.  <br />10. Add’l Owner’s Protective Insurance Policy (COR 9000065): The Contractor incurred additional Builder’s  <br />Risk insurance costs due to the Owner issued work suspension directive.  The Engineer concurs and  <br />recommends this cost change.  <br />a. This change adds Bid Item 0199, CO‐6: Add'l Owner's Protective Insurance Policy: lump sum  <br />quantity of 1.0 LS at the Contract Unit Price of $6,193.00 per LS for a price increase of $6,193.00.  <br />11. Bentonite Grout (COR 9000067): The Engineer directed replacement of water stop material to benefit  <br />the project and reduce the risk of future maintenance issues.  The Contractor incurred additional costs  <br />to complete this work.  The Engineer concurs and recommends this cost change.  <br />a. This change adds Bid Item 0200, CO‐6: Bentonite Grout: lump sum quantity of 1.0 LS at the  <br />Contract Unit Price of $7,401.40 per LS for a price increase of $7,401.40.   <br />12. Concrete Driveway 119 Oxbow Drive (COR 9000069): The Owner and Owner’s Representative agreed to  <br />and directed the Contractor to provide additional driveway apron flare work to match the original