  <br />HMG‐TO‐13‐A7_Long.docx  2  <br />2. Services of Engineer  <br />A. General  <br />i. Red River Levees.  Prepare Preliminary Design Report (PDR) and drawings for the  <br />construction of levees through town. The work will be done in 2 phases: Phase 1 will  <br />include screening of alternatives, preliminary design, and selecting final alignments.   <br />Phase 2 will include detailed plans and specifications.    <br />ii. Support for Upstream Stage Area Levees.  Provide, as requested, assistance to USACE  <br />for design of ring levees and non‐structural improvements in the Upstream Staging  <br />Area.  <br />1. Provide detailed designs for four of the Oxbow/Hickson/Bakke ring levee Work  <br />Packages (WP‐43A, WP‐43C, WP‐43D, and WP‐43E).  <br />B. Scope of Work  <br />i. Red River Levees – Work will be done in 2 phases:  <br />1. Phase 1  ‐ Screening of Alternatives, Selection of Alignment, and Preliminary  <br />Design for the area in Fargo, ND along the Red River between the existing  <br />railroad embankment near 5th Avenue North and the north end of the existing  <br />4th Street levee (near 2nd Street South). Work will include:  <br />a. Development of Alternatives – Develop up to three (3) protection  <br />alignment concepts and conceptual level cost estimates. Participate in  <br />an alignment selection meeting.   <br />b. Public involvement – Meet with affected property owners  <br />(5 anticipated), participate in two (2) public meetings, and respond to  <br />calls after public meetings. Prepare visualizations of alignment  <br />alternatives(s).  <br />c. Surveying – Conduct topographic survey of project corridor including  <br />elevations, utilities, landscaping, buildings, and streets.  <br />d. Geotechnical Exploration and Testing – Determine location of borings,  <br />right‐of‐entry requests, conduct borings, field and laboratory testing,  <br />to determine surface and subsurface geological conditions.  <br />e. Preliminary Geotechnical Analysis – Conduct preliminary stability  <br />analysis on alignment alternatives and report of findings.  <br />f. Preliminary Hydrologic and Hydraulic Analysis  ‐ Conduct HEC‐RAS  <br />modeling to complete preliminary evaluation of Red River stage  <br />impacts due to proposed project.  <br />g. Preliminary Internal Flood Control Analysis – Conduct SWMM model  <br />update for existing conditions and proposed conditions with project  <br />(including consideration of interior ponding), review of historical  <br />precipitation and stream flow, simulation of low river gravity outlet  <br />condition, simulation of high river pumped outlet condition, and  <br />determine preliminary pump sizing and additional internal storage  <br />needs.  <br />h. Preliminary Utility Investigation – Determine preliminary utility  <br />relocation requirements, conduct utility coordination meeting, and  <br />document utility relocation requirements and issues.  <br />DR <br />A <br />F <br />T