<br />Commission Minutes--August 7,2000 2162
<br />
<br />Site Development * 3.0%
<br />Miscellaneous Costs **
<br />Total Construction
<br />
<br />449,178
<br />900,000
<br />16,321,786
<br />
<br />17,026,200
<br />
<br />Programming & Architectural
<br />Fees & Reimbursable 6.3%
<br />
<br />1,028,273
<br />17,350,059
<br />
<br />1,072,651
<br />18,098,851
<br />
<br />Total costs of construction
<br />
<br />Contingency
<br />
<br />249,941
<br />
<br />300,000
<br />
<br />Site Acquisition
<br />Land Purchase
<br />Less Reimbursement from City
<br />Special Assessments Paid
<br />Special Assessments Certified
<br />Special Assessments Estimated
<br />for new Street and Utilities
<br />Total Site Acquisition
<br />
<br />400,000
<br />
<br />400,000
<br />
<br />681,561
<br />(35,000)
<br />11,348
<br />100,000
<br />
<br />174,300
<br />932,208
<br />
<br />Transition Team Budget
<br />Escrow for First Addition 2,000,000
<br />Building Fit Up - 25% of construction 4,000,000
<br />This is an estimate on the cost of the furniture,
<br />fixtures, equipment, supplies, etc to open the building.
<br />These items would include everything form waste baskets,
<br />to desks, chairs, laundry equipment (other than the fixed
<br />equipment in the construction bids), kitchen equipment
<br />(again, other than the fixed equipment in the construction
<br />bids), and jail maintenance equipment. NOTE that the
<br />Transition Plan of December 1999, page 5 of the action
<br />plan calls for the specific list of equipment to be
<br />developed in June of 2001 with specifications and bidding
<br />to be completed by 7/7/2001.
<br />
<br />380,380
<br />1,200,000
<br />3,000,000
<br />
<br />Staffing
<br />Also included in the $3,000,000 - depending on if funds
<br />are available, is the hiring of the new correctional staff
<br />and training them prior to the opening of the jail. These
<br />staff will have to be hired starting in July of 2001 with
<br />a start date of 11/16/2001 so that they can go through
<br />training before the new jail opens, again, see the
<br />Transition Plan of December 1999, page 9 of the action
<br />plan.
<br />
<br />Total estimated cost of jail construction, land
<br />acquisition, transition, furniture/fixtures
<br />and opening costs
<br />
<br />24,000,000
<br />
<br />23,911,439
<br />
|