As of July 18, 2019 <br />Southern Embankment <br />Property Status Report <br />Southern Embankment <br />(WP Reach SE-1 to SE-5 and I29)Targeted Completion: TBD <br />Southern Embankment & <br />Control Structures <br />114 parcels total <br />2 In Negotiation <br />9 Appraisal/ MOU Pending <br />16 Agreement Signed <br />0 Condemnation <br />6 Acquired Parcel <br />Change from last report <br />Hard Costs paid to Property Owners <br />$39.4Mbudgeted <br />$10.4Mspent <br />$2.0Masset property <br />$0.0Mpurchase agreement <br />Spent <br />Asset Property <br />Purchase Agreement <br />Budgeted <br />$40M <br />$30M <br />$20M <br />$10M <br />$0M <br />Page 7 of 9