METRO FLOOD DIVERSION PROJECT <br /> <br /> <br />TAG-ED_CONTRACTING RECOMMENDATION_NAASTADBROTHERS_2018-0924 1 <br />Technical Advisory Group and Executive Director Contracting Recommendation Date: 09/24/2018  <br />RECOMMENDATION FOR ACTION:  <br />The Technical Advisory Group and Co‐Executive Directors have reviewed and recommended approval of the  <br />following Contract Action(s).  <br />SUMMARY OF CONTRACTING ACTION:  <br />Per the contract review and approval procedures that were adopted by the Diversion Authority on November  <br />10, 2016 and amended August 23, 2018, the Owner’s Program Management Consultant (PMC) or Co‐ <br />Executive Directors shall submit a proposed Contract (value >$10,000 and <$150,000) to Technical Advisory  <br />Group for review, and shall consolidate the recommendations of the Technical Advisory Group and the Co‐ <br />Executive Directors onto a single form and submit the written recommendation to the Finance Committee.  <br />The Owner’s PMC has prepared the following Contract Action(s):  <br />Naastad Brothers, Inc. <br />Cass County Road Ditch Work $30,856.40  <br /> Hwy 81 temporary approach removal   <br /> 6,200 LF of CR‐17 ditch cleaning    <br />BACKGROUND AND DISCUSSION:  <br />The PMC has worked with Flood Diversion staff to procure pricing for two (2) construction tasks scheduled to be  <br />done this fall in Cass County roadway ditches.  <br />  <br />The work under this proposed Contract includes the removal of a Hwy 81 temporary approach and approximately  <br />6,100 lineal feet (LF) of CR‐17 ditch cleaning, described below:  <br />   <br />1. Hwy 81 approach removal.  A temporary approach was installed by one of the OHB Ring Levee demolition  <br />contractors to provide better access to a project borrow area.  Now that that work is done, the temporary  <br />approach needs to be removed and the approach removal work was not included in that construction  <br />contract.   <br />2. CR‐17 ditch cleaning.  Approximately 6,200 LF of CR‐17 east and west roadway ditches, north of CR‐16 and  <br />the temporary CR‐17 bypass, need to be cleaned and regraded to facilitate drainage.   <br />The table below summaries the contracting history for this task order and the current contracting action.    <br />SUMMARY OF CONTRACTING HISTORY AND CURRENT CONTRACT ACTION:  <br />Original  <br />Agreement or  <br />Amendment  <br />Budget ($)  <br />Change  <br />Original  <br />Project Cost  <br />Revised  <br />Project Cost  <br />Project  <br />Start  <br />Project  <br />Completion Comments  <br />Service Contract  $30,856.40  27‐Sep‐18 31‐Dec‐18 Hwy 81 temporary approach removal and  <br />6,200 LF of CR‐17 ditch cleaning.  <br />