METRO FLOOD DIVERSION PROJECT
<br />TAG CONTRACTING RECOMMENDATION FORM WP-42A2 IBI CO-11 1
<br />Technical Advisory Group Recommendation Meeting Date: 11/1/2016
<br />RECOMMENDATION FOR ACTION:
<br />The Technical Advisory Group has reviewed and recommends approval of the following Contract Action(s).
<br />SUMMARY OF CONTRACTING ACTION:
<br />The Owner’s Representative has reviewed and recommends the following Contract Action(s):
<br />List description of Contract Action(s):
<br />Description
<br />Budget
<br />Estimate ($)
<br />Industrial Builders, Inc.
<br />Change Order #11 ($36,492.02)
<br />WP-42A.2, 2nd Street North Pump Station – Final Project Cost Adjustment and Decorative
<br />Fence De-Scope
<br />Summary of Contracting History and Current Contract Action:
<br />Original
<br />Agreement or
<br />Amendment
<br />Previous Project
<br />Cost
<br />Budget ($)
<br />Change
<br />Revised Project
<br />Cost Project Start Project
<br />Completion Comments
<br />Original
<br />Contract
<br />0.00 8,069,000.00 8,069,000.00 9-Oct-14 31-Jan-16 Contract Award recommended to
<br />lowest responsive bidder, Industrial
<br />Builders, Inc.
<br />Change Order 1 8,069,000.00 66,920.00 8,135,920.00 9-Oct-14 31-Jan-16 Revisions to traffic control
<br />Change Order 2 8,135,920.00 67,397.00 8,203,317.00 9-Oct-14 31-Jan-16 Accommodate unforeseen
<br />subsurface conditions (remove
<br />concrete structure and dispose of
<br />contaminated soil)
<br />Change Order 3 8,203,317.00 225,056.00 8,428,373.00 9-Oct-14 16-Feb-16 Change in design requirements for
<br />backfill of structure
<br />Change Order 4 8,428,373.00 238,871.75 8,667,244.75 9-Oct-14 25-Apr-16 Baffle wall, sheeting, and 2nd Street
<br />road closure
<br />Change Order 5 8,667,244.75 7,614.93 8,674,859.68 9-Oct-14 25-Apr-16 Physical model tests, vacuum line,
<br />pump station veneer, and cold
<br />weather construction costs.
<br />Change Order 6 8,674,859.68 43,488.99 8,718,348.67 9-Oct-14 7-Dec-16 Completion Milestone Changes,
<br />Extended Warranty Duration,
<br />Modifications to Trash Rack and
<br />Rake, and Check Valve Replacement.
<br />Change Order 7 8,718,348.67 1,870.32 8,720,218.99 9-Oct1-14 7-Dec-16 Pump Station Beacons
<br />Change Order 8 8,720,218.99 (47,876.36) 8,672,342.63 9-Oct-14 7-Dec-16 Deduct unused budget for hazardous
<br />material removal
|