Laserfiche WebLink
METRO FLOOD DIVERSION PROJECT <br /> <br /> <br />TAG_CONTRACTINGRECOMMENDATIONFORM_WP-42A1-A3_CO-05_20160908.DOCX 1 <br />Technical Advisory Group Recommendation Meeting Date: 9/1/2016 <br />RECOMMENDATION FOR ACTION: <br />The Technical Advisory Group has reviewed and recommend approval of the following Contract Action(s). <br />SUMMARY OF CONTRACTING ACTION: <br />The Owner’s Representative has reviewed and recommends the following Contract Action(s): <br />List description of Contract Action(s): <br />Description Budget <br />Estimate ($) <br /> <br />ICS, Inc. <br />Change Order #05 $70,363.71 <br />WP-42A.1/A.3, 4th Street Pump Station – Addition of sanitary sewer overflow connection for emergency use, and T&M <br />budget for additional costs to remove the 78” pipes now known to be coated in asbestos-contaiming material. <br />Summary of Contracting History and Current Contract Action: <br />Original <br />Agreement or <br />Amendment <br />Budget ($) <br />Change <br />Previous Project <br />Cost <br />Revised Project <br />Cost Project Start <br />Project <br />Completion Comments <br />WP-42A.1/A.3 <br />contract <br />17,361,616.35 0.00 17,361,616.35 11-Dec-14 11-Nov-16 Awarded 4th Street Pump <br />Station and 2nd Street South <br />Floodwall <br />Change Order 1 268,555.24 17,361,616.35 17,630,171.59 11-Dec-14 11-Nov-16 Fargo Highrise parking lot <br />modifications and other costs <br />Change Order 2 176,462.97 17,630,171.59 17,806,634.56 11-Dec-14 11-Nov-16 Unknown underground <br />structures and other costs <br />Change Order 3 (10,570.93) 17,806,634.56 17,796,063.63 11-Dec-14 11-Nov-16 Deduct exterior electrical work <br />and install fence, bollards, and <br />lights at Fargo Highrise <br />Change Order 4 15,174.67 17,796,063.63 17,811.238.30 11-Dec-14 11-Nov-16 Time extensions and multiple <br />cost adjustments for Engineer- <br />and Owner-directed items. <br />Work Change <br />Directive 6 <br />17,811,238.30 ~40,000.00 17,851,238.30* 11-Dec-14 11-Nov-16 Install stilling wells for <br />ultrasonic transducers <br />Change Order 5 17,851,238.30* 70,363.71 17,921,602.01* 11-Dec-14 11-Nov-16 Last of suspended changes, <br />sanitary overflow connection, <br />T&M budget for ACM removal <br /> <br />* Includes estimated amount for work to perform WCD-006 (installation of stilling wells) which will be finalized in a future Change Order.