METRO FLOOD DIVERSION PROJECT
<br />TAG CONTRACTING RECOMMENDATION FORM WP-42A2 IBI CO-07 1
<br />Technical Advisory Group Recommendation Meeting Date: 5/19/2016
<br />RECOMMENDATION FOR ACTION:
<br />The Technical Advisory Group has reviewed and recommends approval of the following Contract Action(s).
<br />SUMMARY OF CONTRACTING ACTION:
<br />The Owner’s Representative has reviewed and recommends the following Contract Action(s):
<br />List description of Contract Action(s):
<br />Description
<br />Budget
<br />Estimate ($)
<br />WP-42A.2: Industrial Builders, Inc.
<br />Change Order #7 $1,870.32
<br />WP-42A.2, 2nd Street North Pump Station – Pump Station Beacons
<br />Summary of Contracting History and Current Contract Action:
<br />Original
<br />Agreement or
<br />Amendment
<br />Budget ($)
<br />Change
<br />Original Project
<br />Cost
<br />Revised Project
<br />Cost Project Start
<br />Project
<br />Completion Comments
<br />Original
<br />Contract
<br />$8,069,000.00 $0.00 $8,069,000.00 9-Oct-14 31-Jan-16 Contract Award recommended to
<br />lowest responsive bidder, Industrial
<br />Builders, Inc.
<br />Change Order
<br />No. 1
<br />$66,920.00 $8,069,000.00 $8,135,920.00 9-Oct-14 31-Jan-16 Revisions to traffic control
<br />Change Order
<br />No. 2
<br />$67,397.00 $8,135,920.00 $8,203,317.00 9-Oct-14 31-Jan-16 Accommodate unforeseen
<br />subsurface conditions (remove
<br />concrete structure and dispose of
<br />contaminated soil)
<br />Change Order
<br />No. 3
<br />$225,056.00 $8,203,317.00 $8,428,373.00 9-Oct-14 16-Feb-16 Change in design requirements for
<br />backfill of structure
<br />Change Order
<br />No. 4
<br />$238,871.75 $8,428,373.00 $8,667,244.75 9-Oct-14 25-Apr-16 Baffle wall, sheeting, and 2nd Street
<br />road closure
<br />Change Order
<br />No. 5
<br />$7,614.93 $8,667,244.75 $8,674,859.68 9-Oct-14 25-Apr-16 Physical model tests, vacuum line,
<br />pump station veneer, and cold
<br />weather construction costs.
<br />Change Order
<br />No. 6
<br />$43,488.99 $8,674,859.68 $8,718,348.67 9-Oct-14 7-Dec-16 Completion Milestone Changes,
<br />Extended Warranty Duration,
<br />Modifications to Trash Rack and
<br />Rake, and Check Valve Replacement.
<br />Change Order
<br />No. 7
<br />$1,870.32 $8,718,348.67 $8,720,218.99 9-Oct-14 7-Dec-16 Pump Station Beacons
|