TECHNICAL STAFF RECOMMENDATION
<br />2 TAG CONTRACTING RECOMMENDATION_MFDA-HMG-AWD0058_20160504
<br />DISCUSSION:
<br />WP‐42F.1N (Flood Control, 2nd St. N, North of Pump Station):
<br />Construction for WP‐42F.1N is scheduled to start in May 2016, and this AWD adds the SDC scope and budget for
<br />this work. Attached is HMG’s cost proposal for this work. This cost is shown in the WP‐42 SDB and SDC budget
<br />table summary below.
<br />
<br />WP‐42F.2:
<br />This AWD authorizes scope and budget for SDB for WP‐42F.2, which will go to bid in May 2016. HMG’s proposal
<br />for this work is attached, and the cost is shown in the budget table below.
<br />
<br />WP‐42 SDB and SDC Budgets by Work Package and Amendment:
<br />Work Package Act. ID SDB ($) SDC ($) PM ($) On Call ($) Total ($) Amendment
<br />WP‐42A.2 &
<br />42A.1/A3 CN‐XXXX 50,000 1,300,000 180,000 20,000 1,550,000 TO17‐A0
<br />WP‐42F.1S CN‐XXXX 36,000 540,000 60,000 636,000
<br />TO17‐A1
<br />WP‐42H.2 CN‐XXXX 27,000 27,000
<br />WP‐42I.1 CN‐XXXX 15,000 15,000
<br />WP‐42C.2 CN‐XXXX 15,000 15,000
<br />Subtotal TO17‐A1 93,000 540,000 60,000 0 693,000
<br />WP‐42A.2 CN‐XXXX 192,000 192,000
<br />TO17‐A2
<br />WP42A.1/A3 CN‐XXXX 830,000 28,000 858,000
<br />WP‐42C.1 CN‐XXXX 10,000 22,000 3,000 35,000
<br />WP‐42C.2 CN‐XXXX 40,000 40,000
<br />WP‐42H.2 CN‐XXXX 263,000 38,000 301,000
<br />WP‐42I.1 CN‐XXXX 132,000 25,000 157,000
<br />WP‐42F.1N CN‐XXXX 22,000 22,000
<br />Subtotal TO17‐A2 32,000 1,479,000 94,000 0 1,605,000
<br />WP‐42F.1N CN‐XXXX 0 30,000 0 30,000
<br />AWD‐0058 WP‐42F.2 CN‐XXXX 15,000 0 0 0 15,000
<br />Subtotal AWD‐0058 15,000 30,000 0 0 45,000
<br />
<br />
<br />The PMC reviewed HMG’s revised cost proposals and found it to be acceptable.
<br />This change amount of $45,000 is included in the FY‐2016 FMDA budget.
<br />ATTACHMENT(S):
<br />1. Draft AWD‐0058
<br />
|