TECHNICAL STAFF RECOMMENDATION
<br />
<br />TS CONTRACTING RECOMMENDATION_MFDA-HMG-TO09A15_20160202 3
<br />
<br />DISCUSSION:
<br />For subtasks that have been completed and have budget remaining, that budget was reallocated to tasks that
<br />remain open. There were minor budget overruns (less than $1,000) for subtasks F.I, F.III, and F.VIII.
<br />
<br />Additional costs of $68,184 for meetings and consulting were incurred to support the USACE Maple River
<br />Aqueduct Physical Model.
<br />
<br />Additional scope and budget ($350,493) are requested to complete the Phase 8 modeling task. Work includes:
<br />revising the Phase 8 model to match the Hickson Hydrograph and recalibrate the model, evaluation of RRN
<br />tributary hydrographs, address outstanding review comments, review and incorporate Western Cass Flood
<br />Insurance Study geometry and hydrology, compare Phase 8 model to Phase 7.1 model, and perform QA/QC
<br />reviews.
<br />
<br />Additional scope and budget ($27,537) is requested to support the update (expanded geography) of the NDSU
<br />Agricultural Impacts Study.
<br />
<br />TO09 Hydrology and Hydraulic Modeling Budgets by Subtask:
<br />Subtask Activity ID Current Budget
<br />($)
<br />Amendment 15
<br />($) Total ($)
<br />HMS Diversion Inlet Modeling SW‐1040 22,121 (2,702) 19,419
<br />Updates to Rush/Lower Rush SW‐1050 16,401 (986) 15,415
<br />Evaluation of Channel Size SW‐1040 237,605 (169,422) 68,183
<br />Extend RAS Geometry of Rush/Lower
<br />Rush
<br />SW‐1040 17,714 (11,182) 6,532
<br />Physical Modeling Assistance SW‐1040 10,500 (272) 10,228
<br />ON‐CALL SERVICES (ALLOWANCE) SW‐1040 44,900 0 44,900
<br />F.I. Extreme Rainfall Events SW‐1270 7,500 260 7,760
<br />F.II. Extreme Event Evaluations SW‐1270 26,600 (182) 26,418
<br />F.III Tributary Peak Model Runs to
<br />Support the Maple River Aqueduct
<br />Physical Model
<br />SW‐6100 20,000 81 20,081
<br />F.IV Additional Assistance for the Maple
<br />River Aqueduct Physical Model
<br />SW‐6110 104,00068,184 172,184
<br />F.V Unsteady HEC‐RAS Modeling of
<br />Existing PMF Inflows
<br />SW‐1040 50,000 (3,199) 46,801
<br />F.V Phase 2 Numeric Modeling SW‐1040 60,000 (30,779) 29,221
<br />F.VI Update HEC‐RAS Model SW‐1040 36,000 (29) 35,971
<br />F.VII Connecting Channel and 20‐year
<br />Existing Conditions
<br />SW‐1040 9,000 (2,586) 6,414
<br />F.VIII Maple River Aqueduct Flow
<br />Analysis
<br />SW‐1040 15,000 52 15,052
<br />F.IX Update HEC‐RAS Models – Maple
<br />River Aqueduct & Reach 6 Bridge
<br />SW‐6110 40,000 (4,910) 35,090
<br />F.X Water Monitoring Gage Survey SW‐6080 5,000 (982) 4,018
<br />F.XI. HEC‐RAS Models ‐ Maple River
<br />Aqueduct
<br />SW‐6150 25,000 (4,910) 20,090
|