Laserfiche WebLink
As of November 13, 2019 <br />Southern Embankment <br />Property Status Report <br />Southern Embankment <br />(WP Reach SE-1 to SE-5 and I29)Targeted Completion: September 2025 <br />Southern Embankment & <br />Control Structures <br />124 parcels total <br />0 Condemnation <br />22 Acquired/ TCE Secured <br />Change from last report <br />Hard Costs paid to Property Owners <br />$33.0Mbudgeted <br />$10.4Mspent <br />$2.4Masset property <br />$0.4Mpurchase agreement <br />Spent <br />Asset Property <br />Purchase Agreement <br />Budgeted <br />$40M <br />$30M <br />$20M <br />$10M <br />$0M <br />SE-1 SE-2 <br />SE-3 <br />SE-4 SE-5 <br />10 In Negotiation <br />57 Appraisal/ MOU Pending <br />0 Agreement Signed <br />I29 <br />ND <br />MN <br /> <br />Page 7 of 10