X:\PROJECTS\SA\SA_Fargo_Moorhead_Metro(PED)-370365\1_Project_Management\Schedule\2019-06-21a_Construction_Bar_Chart.xlsx 6/25/2019 <br />Fargo-Moorhead Metropolitan Area Flood Risk Management Project <br />Federal Construction Placement - As of June 2019 <br />Actual schedule dependent on Funding <br />P&S Approved <br />(BCOES Signoff)Contract Award <br />Construction <br />SubstantiallyComplete <br />O N D J F M A MJ J A S OND J F MA M J J A S O N D J F M A MJ J A S O N DJ F MA MJ J A S ON D J F MA M J J A S O N D J F M A MJ J A S OND J F MA M J J A S O N D J F M A MJ J A S O N DJ F MA MJ J A S ON D J F MA M J J A S O N D J F M A MJ J A S OND J F MA M J J A S O N D J F M A MJ J A S <br />Diversion Inlet Structure (ND)May 2016 (actual)Dec 2016 April 2022 <br />Land acquisition for Inlet Structure <br />Wild Rice River Structure (ND)May 2019 (actual)Sep 2019 Oct 2023 <br />Land acquisition for Wild Rice River Structure <br />I-29 Bridge/Raise (ND)Oct 2020 Jan 2021 Jan 2024 <br />Land acquisition for I-29 <br />Red River Structure (ND/MN)Aug 2021 Dec 2021 Nov 2025 <br />Land acquisition for Red River Structure <br />PER for Southern Embankment Reach SE-1 Dec 2019 N/A N/A <br />Southern Embankment Reach SE-1 (ND)Jul 2020 Sep 2020 Nov 2021 <br />Land acquisition for Reach SE-1 <br />PER for Southern Embankment (remaining Reaches SE-2 - 5)Dec 2020 N/A N/A <br />(Final complete) <br />Southern Embankment Reach SE-2A (ND)Nov 2021 Feb 2022 Mar 2024 <br />Land acquisition for Reach SE-2A <br />Southern Embankment Reach SE-2B (ND)Oct 2022 Jan 2023 Feb 2025 <br />Land acquisition for Reach SE-2B <br />Southern Embankment Reach SE-3 (ND)Sep 2025 Dec 2025 Dec 2026 <br />Land acquisition for Reach SE-3 <br />Southern Embankment Reach SE-4 (MN)Oct 2023 Jan 2024 Apr 2026 <br />Land acquisition for Reach SE-4 <br />Southern Embankment Reach SE-5 (MN)Sep 2024 Dec 2024 Jan 2026 <br />Land acquisition for Reach SE-5 <br />Drayton Dam (MN)Sep 2019 May 2021 Jul 2022 <br />Land acquisition for Drayton Dam <br />Horace Plug Removal (ND)Sep 2026 Sep 2027 Sep 2028 <br />Land acquisition for Horace Plug Removal <br />Sheyenne Oxbow Restoration (ND)Sep 2026 Sep 2027 Sep 2028 <br />Land acquisition for Sheyenne Oxbow Restoration <br />Aquatic Restoration Projects TBD Aug 2021 TBD <br />Land acquisition for aquatic restoration projects <br />Wetland Restoration TBD TBD TBD <br />Land acquisition for Wetland Restoration <br />Floodplain Forest Restoration TBD TBD TBD <br />Land acquisition for Floodplain Forest Restoration <br />Cultural Resources Mitigation N/A Jun 2019 TBD <br />Other Activities <br />Upstream Land Acquisition <br />OHB Design / EDC for Reach 43B <br />Operation Manual <br />Project Operational <br />Legend <br />Various contracts <br />Various contracts. 1st task order awarded in June 2019. <br />Various contracts <br />Construct prior to or concurrent with Red River Structure <br />Eastern Tieback and Wolverton Creek Crossing <br />Construct after project operational (assume P3 contract operational <br />April 2026, Reach SE-3 complete Dec 2026) <br />Construct after project operational (assume P3 contract operational <br />April 2026, Reach SE-3 complete Dec 2026) <br />Various contracts. Prior to or concurrent with RRS. Award date is for <br />first contract. <br />Notes <br />Contract suspended 9/8/2017 through 4/15/2019. Actual contract <br />completion date TBD. <br />Lands acquired for base contract. Need lands for option. <br />2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 <br />Red River Structure to 180th Ave S (county line) <br />Diversion Inlet Structure to Drain 27. <br />Design and EDC by sponsor; construction and CM by Corps. Assume <br />4 years construction. <br />Assume 4 years construction. <br />Western Tieback. Assume 1 year construction (2 years if slurry wall <br />is required). <br />Wild Rice River Structure to Red River Structure. Assume 1 year <br />construction. <br />Drain 27 to Wild Rice River Structure. <br />Scheduled Design for each construction contract (Blue/right slashed fill) <br />Land Acquisition (Green/dotted fill) <br />2028Project Construction Period by Federal Fiscal Year (FY) <br />Suspension <br />Estimated Construction (Red/no pattern fill) <br />Feature <br />Complete concurrent with construction and prior to project <br />operation (Corps audit activities) <br />Project operation after construction and upstream land acquisition <br />complete <br />Final available after last contract complete <br />Corps design, sponsor construction <br />Vegetation Establishment (Light red/left slashed fill) <br />Assume Diversion Channel Operational