As of June 1, 2017 <br />Southern Embankment <br />Property Status Report <br />Parcel Status <br />Parcel Status <br />6 parcels total <br />7 parcels total <br />4 Acquired <br />2 Remain <br />7 Remain <br />Wild Rice Control StructureTarget Completion: May 2018 <br />Red River Control StructureTarget Completion: May 2019 <br />ND EmbankmentTarget Completion: May 2019 <br />Parcel Status <br />19 parcels total <br />19 Remain <br />28 Remain <br />16 Remain <br />MN EmbankmentTarget Completion: May 2020 <br />Limited Service SpillwayTarget Completion: May 2021 <br />Parcel Status <br />Parcel Status <br />28 parcels total <br />16 parcels total <br />In Negotiation <br />Appraisal Pending <br />Agreement Signed <br />Condemnation <br />Acquired Parcel <br />Changed from last report <br />(Part of ND Embankment) <br />(Part of ND Embankment) <br />Page 8 of 11