Laserfiche WebLink
Recommended_Contracting_Actions_Summary_2016_1013.docx <br /> <br />Description Company Budget <br />Estimate ($) <br />Construction Change Orders <br />6.a.3 WP-42A.1/A.3, 4th Street Pump Station <br />Change Order 06 <br />• Stilling wells and other outstanding change items <br />ICS, Inc. 147,079.47 <br />6.a.4 WP-42F.1N 2nd Street North (North of Pump Station) <br />– Change Order 03 <br />• Plan sheet Updates, Retaining Wall Column, 6” Impressioned <br />Concrete, Additional Bridge Lighting <br />Industrial <br />Builders, Inc. <br />(22,030.50) <br />6.a.5 WP-42F.1S Flood Control – 2nd St. N., South of Pump <br />Station, Change Order 13 <br />• Utility Vault Adjustment, 1st Ave N Bridge Spall Removal, <br />42A2 Pump Station Elevation Discrepancy, Flared End Section <br />Riprap, and Case Plaza Parking Lot <br />Industrial Builders, <br />Inc. <br />75,899.63 <br />6.a.6 WP-42F.2 Flood Control, 2nd Street South, <br />Change Order 01 <br />• Additional Traffic Control, Differing Subsurface Conditions, <br />Repair Existing Storm Sewer Catch basin Casting, 4” Gate Valve, <br />4” Waterman, Setting Manhole ST 3, 6” Gate Valve and Pipe, <br />Pavement Markings, Unsuitable Material, Plan Updates. <br />• Administrative Change Regarding Owner’s Representative and <br />Engineer Responsibilities <br />Hough, Inc. of <br />Detroit <br />Lakes <br />206,886.08 <br />6.a.7 WP-42H.2 El Zagal Area Flood Risk Management – <br />Phase 2, Change Order 03 <br />• Floodwall pier caps, sanitary lift station start-up, sidewalk tree <br />removal, storm inlet structure casting, and property drainage <br />adjustment. <br />Reiner Contracting <br />Inc. <br />9,401.21 <br />Total Construction Change Orders 417,235.89 <br />