TECHNICAL ADVISORY GROUP RECOMMENDATION <br />TAG CONTRACTING RECOMMENDATION_MFDA-HMG-TO10A8_20160707 <br />DISCUSSION: <br />Amendment 8 to Task Order 10 adds scope and budget for additional work under the Relocation Design <br />Allowance and Red River Levees Utility Relocation Plan. <br />For Subtask 2.C (Relocation Design Allowance), the work performed to complete designs exceed the $30,000 <br />allowance by $400. This is approximately 2-3 hours of labor and is less than five percent of the total allowance. <br />The PMC recommends increasing this subtask budget $400 to cover this additional work. <br />For Subtask 2.A3 (Red River Levees Utility Relocation Plan), HMG provided a cost proposal for additional planning <br />and coordination work undertaken to complete utility relocation designs that cross the 2nd Street North floodwall <br />and obtain USACE approval of the designs. The additional work was required for six (6) utility relocations and <br />adds 112 hours of labor at a cost of approximately $15,100. The PMC reviewed this cost proposal and <br />recommends increasing this subtask budget $15,100 to cover this additional work. <br />TO10 Utility Relocation and Identification Budgets by Subtask: <br />Subtask Activity ID Current Budget <br />($) <br />Amendment 8 <br />($) Total ($) <br />NORTH <br />2A-1. Utility Relocation Plan SW-1250 37,000 0 37,000 <br />2B. Utility Relocation Services for <br />Specific Utility Owners SW-1250 22,000 0 22,000 <br />2C. Relocation Design <br />(Allowance) SW-1250 30,000 400 30,400 <br />2D. Relocation Support Services SW-1250 5,000 0 5,000 <br />SOUTH <br />2A-2. Utility Relocation Plan SW-1250 194,000 0 194,000 <br />RED RIVER LEVEES <br />2A-3. Utility Relocation Plan SW-1250 50,000 15,100 65,100 <br />TOTAL 338,000 15,500 353,500 <br />The PMC reviewed HMG’s cost proposal and found it to be acceptable. <br />This change amount of $15,500 is included in the FY-2016 FMDA budget. <br />ATTACHMENT(S): <br />1.Draft Task Order 10, Amendment 8 <br />2.HMG cost proposal