<br />HMG_TO08-A13_Long 12
<br />Subtask Start Time Completion Time
<br /> E.IV-Geomorphology Consulting December 13, 2012 September 30, 2015
<br /> E.V-MN EIS Scoping Document Comment Support April 24, 2013 September 30, 2014
<br /> E.VI-MN EIS Preparation Support February 13, 2014 December 31, 2016
<br />E.VII-Cemetery Assessment Team Support October 9, 2014 December 31, 2016
<br />E.VIII-Large Structure Team Support October 9, 2014 December 31, 2016
<br />E.IX-Hydraulic Structures Aesthetics Evaluation December 11, 2014 December 31, 2016
<br />E.X-Baseline Stream Bank Erosion Evaluation December 11, 2014 December 31, 2016
<br />E.XI-LFC Modeling: Maple River to Diversion Inlet February 5, 2015 December 31, 2016
<br />
<br />5. Payments to Engineer
<br />A. Owner shall pay Engineer for services rendered as follows:
<br />I. Compensation for services identified under Subtasks A through E shall be on a Time and
<br />Material basis in accordance with the Standard Hourly Rates shown in Appendix 2 of
<br />Exhibit C of the Agreement.
<br />II. The total compensation for services identified under the Task Order for Subtasks A
<br />through E is not-to-exceed amount as defined in the table below.
<br />III. Estimated budget for Subtask B, Identification and Assessment of Tie-Back Levees,
<br />Subtask C, Diversion Inlet Gates, and Subtask E, On-Call Services, are based on an
<br />allowance.
<br />1. Engineer will notify Owner when eighty percent (80%) of the budget on Subtask
<br />B, Identification and Assessment of Tie-Back Levees, Subtask C, Diversion Inlet
<br />Gates, and Subtask E, On-Call Services, is expended.
<br />2. Engineer will prepare and submit an amendment for additional compensation
<br />when ninety percent (90%) of budget on Subtask B, Identification and
<br />Assessment of Tie-Back Levees, Subtask C, Diversion Inlet Gates, or Subtask E,
<br />On-Call Services, is expended.
<br />3. Engineer will not perform work beyond one hundred percent (100%) of the
<br />budget for Subtask B, Identification and Assessment of Tie-Back Levees,
<br />Subtask C, Diversion Inlet Gates, or Subtask E, On-Call Services, without
<br />Owner’s authorization by an amendment to this Task Order.
<br />Subtask Activity ID
<br />Current
<br />Budget
<br />($)
<br />Change
<br />($)
<br />Revised
<br />Budget
<br />($)
<br />A. Meander Belt Width Analyses SW-1010 307,203 0 307,203.00
<br />B. Identification and Assessment of Tie-
<br />Back Levees
<br />SW-1040 45,089.96 0 45,089.96
<br />C. EMB Openings (Allowance) SW-1040 39,989 0 39,989.00
<br />D. Diversion Inlet Gates (Allowance) SW-1040 55,418 0 55,418.00 DRAFT
|