METRO FLOOD DIVERSION PROJECT
<br />
<br />
<br />TAG CONTRACTING RECOMMENDATION FORM WP-42F1S IBI CO-06 20160425 1
<br />Technical Advisory Group Recommendation Meeting Date: 5/5/2016
<br />RECOMMENDATION FOR ACTION:
<br />The Technical advisory Group has reviewed and recommends approval of the following Contract Action(s).
<br />SUMMARY OF CONTRACTING ACTION:
<br />The Owner’s Representative has reviewed and recommends the following Contract Action(s):
<br />List description of Contract Action(s):
<br />Description
<br />Budget
<br />Estimate ($)
<br />
<br />Industrial Builders Inc.
<br />Change Order #6 89,243.21
<br />WP‐42F.1S, 2nd Street North (South of Pump Station) –modification of floodwall contract interface and incentive &
<br />disincentive changes to the Agreement
<br />
<br />Summary of Contracting History and Current Contract Action:
<br />Original
<br />Agreement or
<br />Amendment
<br />Budget ($)
<br />Change
<br />Original Project
<br />Cost
<br />Revised Project
<br />Cost Project Start
<br />Project
<br />Completion Comments
<br />Original
<br />Contract
<br />$0.00 $16,184,905.85 $16,184,905.85 08‐Oct‐15 15‐Jun‐17 Contract Award recommended to
<br />lowest responsive bidder, Industrial
<br />Builders, Inc.
<br />Change Order
<br />No. 1
<br />$0.00 $16,184,905.85 $16,184,905.85 08‐Oct‐15 15‐Jul‐17 Adds 30 days to the Contract Time,
<br />revises Interim Milestone A work
<br />items, and adds an option for
<br />descoping a portion of the Work
<br />Change Order
<br />No. 2
<br />$169,490.20 $16,184,905.85 $16,354,396.05 08‐Oct‐15 15‐Jul‐17 Incorporates Work revisions to allow
<br />work around utility lines
<br />Change Order
<br />No. 3
<br />$96,806.17 $16,354,396.05 $16,451,202.22 08‐Oct‐15 15‐Jul‐17 Water main, traffic poles, traffic
<br />control plan, Milestone A scope
<br />Change Order
<br />No. 4
<br />$6,985.96 $16,451,202.22 $16,458,188.18 08‐Oct‐15 15‐Jul‐17 Bridge Lighting, concrete disposal,
<br />winter traffic control, extend 4th St
<br />signal mods requirement
<br />Change Order
<br />No. 5
<br />$68,743.01 $16,458,188.18 $16,526,931.19 08‐Oct‐15 15‐Jul‐17 Concrete grading within pump
<br />station, Unit price change, additional
<br />H Pile, bridge abutment seal, traffic
<br />signals, bridge abutment concrete
<br />disposal and floodwall connections.
<br />Change Order
<br />No. 6
<br />89,243.21 16,526,931.19 16,616,174.40 08‐Oct‐15 15‐Jul‐17 10 Feet of additional flood wall,
<br />incentive and disincentive changes
<br />to the Agreement.
<br />
<br />
|