Changes since 2012 Estimate -Channel <br />2016 Estimate Reduced by $52M due to: <br />Earthwork decreased by $17M <br />Channel width decreased south of I-94 from 300 ft bottom width to 220 ft <br />Earth work reduced from 51M cy to 46M cy <br />Diesel fuel (28,000,000 gal) costs reduced by $35M