<br />REIMBURSEMENT AGREEMENT SUMMARY <br />Xcel Energy <br />Cost Reimbursement Agreement - RA-XL0003 Add $ 16,275.85 <br />Utility Relocation Work <br />Description: <br />This Cost Reimbursement Agreement directs Xcel Energy, to provide all labor, materials, and commissioning <br />necessary to install the 75 KVA transformer that is needed to provide electrical service to the basketball <br />court and warming house on 4th St S. <br />Background: <br />The 75 KVA is required for the electrical service to the basketball court and warming house, a component of <br />the Diversion Authority’s WP-42A.1/A.3 4th Street pump station and 2nd St. S Floodwall Project. <br />Recommendation: <br />The budget of $ 16,275.85 is less than the remaining estimated unencumbered FY 2015 FMDA Construction <br />budget of $ 25,651,000. PMC recommends authorization of Cost Reimbursement Agreement RA-XL0003 for <br />$ 16,275.85. <br /> <br />Recommended_Contracting_Actions_Summary_2015-0910.docx 4