Laserfiche WebLink
<br />ICS, Inc. ADD $268,555.24 <br />Change Order No. 1 <br />WP-42A.1/42A.3 (4th Street Pump Station) <br />Description: <br />Change Order No. 1 includes three distinct elements: <br />1. Change the design for modification of the Fargo Highrise parking lot to maximize the number of parking <br />spaces on site. <br />Cost = $138,154.11 <br />2. Re-route electrical service to the Park District’s warming house to replace a line that had to be removed <br />for the project. <br />Cost = $49,834.89 <br />3. Install approximately 40 feet of new 36” storm sewer line by means of boring where it passes <br />underneath an existing 16” sanitary sewer force main. <br />Cost = $80,566.24 <br />Background: <br />1. Following original design completion, appraisal process for Fargo Highrise revealed that additional <br />parking would be necessary to minimize the impact of the project to the facility owner. HMG redesign <br />parking lot modifications to make maximum use of available space for parking. <br />2. Electrical service to the warming house passed directly through the pump station footprint and must be <br />replaced. <br />3. Design plans and city as-builts showed an existing 16” sanitary sewer force main as ductile iron piping. <br />Contractor’s excavation discovered that force main is actually cast iron piping which could be damaged <br />by further excavation. Risk and cost analysis by Contractor, CH2M HILL, HMG, and City of Fargo <br />concluded that boring the new storm sewer under the existing force main will minimize risk and cost to <br />Owner. <br />Recommendation: <br />PMC recommends authorization of Change Order No. 1 for $268,555.24. <br />AWD_CHANGE-ORDER_SUMMARY_2015-0514.DOCX 3 <br />DR <br />A <br />F <br />T