<br />information concerning available utility services and lines, both public and private, above and below grade,
<br />including inverts and depths. All the information on the survey shall be referenced to a Project benchmark.
<br />
<br />§ 2.2.1.3 The Owner shall fumish services of geotechnical engineers which may include but are not limited to test
<br />borings, test pits, determinations of soil bearing values, percolation tests, evaluations of hazardous materials, ground
<br />corrosion tests and resistivity tests, including necessary operations for anticipating subsoil conditions, with reports
<br />and appropriate recommendations.
<br />
<br />ARTICLE 2.3 EVALUATION AND PLANNING SERVICES
<br />§ 2.3.1 The Architect shall. provide a preliminary evaluation of the information furnished by the Owner under this
<br />Agreement, including the Owner's program and schedule requirements and budget for the Cost of the Work, each in
<br />terms of the other. The Architect shall review such information to ascertain that it is consistent with the requirements
<br />of the Projectand shalLnotify the Owner of any other information or consultant services that may be reasonably
<br />needed for the Project.
<br />
<br />§2.3.2 The Architect shall provide a preliminary evaluation of the Owner's site for the Project based on the
<br />information provided by the Qwner of site conditions, and the Owner's program, schedule and budget for the Cost
<br />of the Work.
<br />
<br />§ 2,3.3 The Architect shall review the Owner's proposed method of contracting for construction services and shall
<br />notify the Owner of I:U1ticipatedirnpacts that such method may have on the Owner's program, financial and time
<br />requirements, andthescopeofthe Project.
<br />
<br />ARTICLE 2.4 DESIGN SERVICES
<br />§ 2.4.1 The Architect's design services shall include normal structural, mechanical and electrical engineering
<br />services.
<br />
<br />§ 2.4.2 SCHEMATIC DESIGN DOCUMENTS
<br />§ 2.4.2.1 The Architectshall provide Schematic Design Documents based on the mutually agreed-upon program,
<br />schedule, and budget for the Cost of the Work. The documents shall establish the conceptual design of the Project
<br />illustrating the scale and relationship of the Project components, The Schematic Design Documents shall include a
<br />conceptual site plan, ifappropriate, and preliminary building plans, sections and elevations. At the Architect's
<br />option, the Schematic Design Docmnentsmay include study models, perspective sketches, electronic modeling or
<br />combinations of these media. Preliminary selections of major building systems and construction materials shall be
<br />noted on the drawings or described in writing.
<br />
<br />§ 2.4.3 DESIGN DEVELOPMENT DOCUMENTS
<br />§ 2.4.3.1 The Architect shalLprovide .Design Development Documents based on the approved Schematic Design
<br />Documents and updated budgetforthe Cost of the Work. The Design Development Documents shall illustrate and
<br />describe the refinement of the design of the Project, establishing the scope, relationships, forms, size and appearance
<br />ofthe Project by mel:U1s of p sections and elevations, typical construction details, and equipment layouts, The
<br />Design Development Doeu shall include specifications that identify major materials and systems and establish
<br />in general their quality levelS.
<br />
<br />§ 2.4.4 CON.STRUCTION DOCUMENTS
<br />§ 2.4.4.1 The Architect shall provide Construction Documents based on the approved Design Development
<br />Documents and updated budget for the Cost of the Work. The Construction Documents shall set forth in detail the
<br />requirements for construction of the Project. The Construction Documents shall include Drawings and
<br />Specifications that establish in detail the quality levels of materials and systems required for the Project.
<br />
<br />§2.4.4.2 During the development of the Construction Documents, the Architect shall assist the Owner in the
<br />development and preparation of: (1) bidding and procurement information which describes the time, place and
<br />conditions of bidding; bidding or proposal forms; and the form of agreement between the Owner and the Contractor;
<br />and (2) the Conditions of the Contract for Construction (General, Supplementary and other Conditions). The
<br />Architect also shall compile the Project Manual that includes the Conditions of the Contract for Construction and
<br />Specifications and may include bidding requirements and sample forms.
<br />
<br />AlA Document 8141'" -1997 Part 2. Copyright @ 1917,1926,1948,1951,1953,1958,1961,1963,1966, 1967, 1970, 1974,1977,1987 and 1997 by The
<br />American Institute of Architects. All rights reserved. WARNING: This AiA~ Document is protected by U.S. Copyright law and international Treaties.
<br />Unauthorized reproduction or distribution of this AlA" Document, or any portion of It, may result in severe civil and criminal penalties, and will be
<br />prosecuted to the maximum extent possible under the law. This document was produced by AlA software at 09:58:48 on 10/29/2004 under Order
<br />No.1000091736_1 which expires on 1/12/2005, and is not for resale.
<br />User Notes:
<br />
<br />3
<br />
<br />(3349938724)
<br />
|