<br />Construction Worksheet
<br />Project:
<br />Date:
<br />
<br />Division
<br />
<br />1 - General Conditions
<br />
<br /> Bid Quantity Labor Material Subcontract
<br />Description Quantity Unit Unit Amount Unit Amount Unit Amount
<br />Contingency Allowance $0,00 $0,00 $0,00
<br />Project Coordination 5 mths $0,00 $0,00 $5,000,00 $25,000,00
<br />Testing 1 ea $0,00 $0,00 $2,000,00 $2,000,00
<br />Temporary phone 5 mths $0,00 $0,00 $200,00 $1,000,00
<br />Temporary toilet 5 mths $0.00 $0,00 $150,00 $750,00
<br />Field Office 5 mths $0,00 $0,00 $350,00 $1,750,00
<br />Project sign 1 ea $0,00 $0.00 $500.00 $500,00
<br />Rough cleaning 4000 sf $0.00 $0,00 $0,50 $2,000,00
<br />Final cleaning 4000 sf $0,00 $0,00 $0,20 $800,00
<br />Bldg permit 1 ea $0,00 $0,00 $3,500,00 $3,500,00
<br />Temporary storage facilities $0,00 $0.00 $0,00
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />Subtotal $0.00 $0,00 $37,300,00
<br />Total $37,300,00