Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute shall <br /> be included as provided in Section 7.3.9 of AIA Document A201TM-2007,General Conditions of the <br /> Contract for Construction; <br /> .2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and <br /> suitably stored at the site for subsequent incorporation in the completed construction(or,if approved in <br /> advance by the Owner,suitably stored off the site at a location agreed upon in,writing),less retainage of <br /> Ten percent( 10%); <br /> .3 Subtract the aggregate of previous payments made by the Owner;and <br /> .4 Subtract amounts,if any, for which the Architect has withheld or nullified a Certificate for Payment as <br /> provided in Section 9.5 of AIA Document A201-2007. <br /> § 5,1.7 The progress payment amount determined in accordance with Section 5.1.6 shall be further modified under the <br /> following circumstances: <br /> .1 Add,upon Substantial Completion of the Work,a sum sufficient to increase the total payments to the <br /> full amount of the Contract Sum, less such amounts as the Architect shall determine for incomplete <br /> Work,retainage applicable to such work and unsettled claims; and <br /> (Section 9.8.5 of AIA Document A201-2007 requires release of applicable retainage upon Substantial <br /> Completion of Work with consent of surety, if any.) <br /> .2 Add,if final completion of the Work is thereafter materially delayed through no fault of the Contractor, <br /> any additional amounts payable in accordance with Section 9.10.3 of AIA Document A201-2007. <br /> 5.1.8 Reduction'or limitation of retainage,if any shall be as follows: <br /> (If it is gitended,prior to Substantial Completion of the entire Work, to reduce or limit the retainage resultingfrom the <br /> percentages inserted in Sections 5.1.6.1 and 5.1.6.2 above, and this is not explained elsewhere in the Contract <br /> Documents„insert here provisions for such reduction or limitation.) <br /> The Architect will authorize payment of 100%of the amount completed after a total of 5%of the Contract amount has <br /> been retained,'providing progress on the Work is in accordance with or ahead of the Contractor's construction <br /> schedule and is satisfactory to the Architect and if the Contractor has filed a Consent of Surety with the Architect. <br /> § 5.1.9 Except with the Owner's prior approval,the Contractor shall not make advance payments to suppliers for <br /> materials or equipment which have not been delivered and stored at the site. <br /> § 5.2 FINAL PAYMENT <br /> § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the <br /> Contractor when <br /> .1 the Contractor has fully performed the Contract except for the Contractor's responsibility to correct <br /> Work as provided in Section 12.2.2 of AIA Document A201-2007,and to satisfy other requirements,if <br /> any which extend beyond final payment;and <br /> .2 a final Certificate for Payment has been issued by the Architect. <br /> § 5.2.2 The Owner's final payment to the Contractor shall be made no later than 30 days after the issuance of the <br /> Architect's final Certificate for Payment,or as follows: <br /> N/A <br /> ARTICLE 6 DISPUTE RESOLUTION <br /> § 6.1 INITIAL DECISION MAKER <br /> The Architect will serve as Initial Decision Maker pursuant to Section 15.2 of AIA Document A201-2007,unless the <br /> parties appoint below another individual,not a party to this Agreement,to serve as Initial Decision Maker. <br /> (If the parties mutually agree, insert the name,address and other contact information of the Initial Decision Maker, if <br /> other than the Architect) <br /> AIA Document A101 TM-2007.Copyright©1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997 and 2007 by The American <br /> Init. Institute of Architects.All rights reserved.WARNING:This AIA Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 4 <br /> reproduction or distribution of this AIA Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the <br /> maximum extent possible under the law.This document was produced by AlA software at 14:43:39 on 04/17/2014 under Order No.0550464256_1 which expires <br /> on 03/14/2015,and is not for resale. <br /> User Notes: (861498489) <br />